Work contract, fixed price, handover, payment.

The terms of our framework contract are here before you apply. A clause that only turns up at signing costs the trust a building site runs on.

A work contract, not hourly work

You owe a result: the finished trade, to the manufacturer specification and the client firm’s design. How you get there, with how many people and in what order, is your decision. We tell you the what, the date and the handover point — not who holds which spanner.

That is the whole difference between a subcontractor and a hired-out fitter, and it is not a formality: social security, tax and liability for both sides hang on it.

One fixed price per type of job

For every type of job — complete installation, core drilling, buried line, foundation, electrical connection — we agree a fixed price in the framework contract. The individual order then names the date, the building and the sum. If something is added that is not in the order, there is an amendment with a new contract sum (§ 650b BGB) before anyone carries on working.

We do not quote guide prices on this page. Journey, building and scope differ too much; a number here would be unfair either to us or to you.

The client supplies the material

Equipment, pipes, fittings, insulation, cable and small parts all come from the client firm through us. You bring people, a vehicle, tools and machines. That way your money is not tied up in our project, and we do not argue about material prices.

Handover on the last day

Handover takes place on site, with a written record, defects and reservations. Only then do the warranty and the payment period begin — and only then do you write the invoice. A defect in the record is a task with a deadline; one that is not in it does not come back later as a deduction.

Payment

The payment term is 21 days after the invoice has been checked. On longer jobs instalments are possible (§ 632a BGB). We accept electronic invoices (XRechnung, ZUGFeRD) and PDF.

Two things can reduce your payment, and both are in your hands: Without a Freistellungsbescheinigung we must pay 15 % of the invoice to your tax office as construction withholding tax (§§ 48 ff. EStG) — it is credited to you, but later. And if you provide a construction service to us, we owe the VAT (§ 13b UStG): your invoice then shows no VAT but a reference to the reverse charge.

If it does not work out

The framework contract can be terminated with 4 weeks’ notice, in writing, without a reason. Individual orders already running are completed. We answer questions about a running job within 24 hours and expect the same.

No VOB/B

Our contracts deliberately do not incorporate the VOB/B. Alongside our own clauses it loses its privileged status (§ 310 (1) sentence 3 BGB), and every single VOB rule would then face the standard-terms test. German work contract law under the BGB applies.

This page summarises standard terms and is not legal advice. The signed contract is what counts.

Standard terms

At a glance

Framework contract · default Sheet 1 / 1
Type of contract
Work contract, BGB
Remuneration
Fixed price per type of job
Material
supplied by the client
Handover
on site with a written record
Payment term
21 days after checking
Retention
5 %, replaceable by a guarantee
Warranty
5 years
Liquidated damages
0,2 % per working day, max. 5 %
Client protection
12 months, mutual
Liability insurance
at least 3 Mio. €
Notice period
4 weeks, in writing
Response time
24 hours

Negotiable case by case. Where a figure has a statutory limit, the contract names it: retention up to 5 %, payment term up to 30 days (§ 308 no. 1a BGB).

Questions

About the terms

Why no hourly rate?

Because a subcontractor who invoices by the hour and works under instruction is not a subcontractor in law. That ends at the audit with contributions due from both sides. A fixed price per project is not a saving trick for us, it is the condition under which the model works at all.

Who is liable if something is damaged on site?

You are, through your liability insurance — which is why it is a mandatory document and must cover at least 3 Mio. €. Defects in your own trade are covered by the 5-year warranty.

What does the retention mean?

We retain 5 % of the settled sum as security for the warranty and pay it out afterwards. You can replace it with a bank guarantee at any time and receive the money immediately.

What are liquidated damages of 0,2 % a day?

If an agreed date is missed without reason, it costs 0,2 % of the contract sum per working day, up to 5 %. There is no mistrust behind this, only our own schedule: at the end of the chain an end customer is waiting without heating.

What does client protection mean?

Anyone you get to know through us, you do not approach yourself for 12 months. In return we stay away from your clients. Without that clause we could not name our client firms to you.

Is there filming on site?

We use cameras to document individual stages of the work. An annex to the framework contract governs this: no monitoring of performance or conduct, notice to everyone involved, the right to object under Art. 21 GDPR, deletion after the agreed period.